Weaver Bottoms
monitoring study: Determining the pros and cons of a rehabilitation
project
by Dr. Mary Davis,
U.S. Army Engineer Waterways Experiment Station
The banks and marshes of the Mississippi River have always
provided healthy environments for many species of wildlife. In the early
1930s, the U.S. Army Corps of Engineers constructed a series of locks
and dams in the Upper Mississippi River to improve navigation along the
river from Cairo, Ill. to Minneapolis, Minn. Extensive areas of the
floodplain were inundated and rapidly became highly productive backwater
marshes. Since the early 1960s, however, acreage and vegetation density
have fluctuated and gradually declined, lowering the quality of existing
wetlands.
Project design
The Great River Environmental Action Team (GREAT) I
was organized in 1973 to identify and assess problems associated with
multipurpose use of the Upper Mississippi River and to develop
recommendations for improved management of its resources. Weaver
Bottoms, a 4,000-acre backwater area located between southeastern
Minnesota and southwestern Wisconsin, was chosen as a representative
site for a study of the marsh problems. An initial assessment of the
site attributed the marshes inability to recover to a variety of
reasons, including
- two major floods in the late 1960s,
- plant damage by wind and ice,
- the constant change in flow and sedimentation patterns, and
- reduced water clarity caused by wind-induced waves due to
resuspension of sediments.
As a result, the Weaver Bottoms Rehabilitation Project was designed
to do two things: (1) to reduce Mississippi River flows entering the
backwater by modifying side channels, and (2) to reduce wind fetch and
re-suspension of bottom sediments by creating barrier islands. In
addition, the project was to reduce maintenance dredging requirements in
the navigation channel and to provide long-term dredged material
storage. The Weaver Bottoms project was to be completed in two phases.
Phase I construction was completed during fall of 1986 and summer of
1987. Partial or complete closures were constructed across most of the
secondary channels leading from the Mississippi River into Weaver
Bottoms, and two 16-acre islands were constructed in open water areas.
Phase II will be the construction of additional islands and/or
implementation of other measures once the effects of Phase I
construction are thoroughly evaluated and recommendations for Phase II
can be made.
Planning and evaluation
An important part of the project was a comprehensive 10-year
Resource Analysis Plan to monitor project effects. An interagency
Memorandum of Understanding (1986), assigned leadership for the
monitoring project to the U.S. Fish and Wildlife Service with active
participation from the Corps and Wisconsin and Minnesota Departments of
Natural Resources.
The Resource Analysis Plan called for an
assessment of project impacts on hydrodynamics; sedimentation; water
quality; emergent and aquatic vegetation; use of aquatic and wildlife
habitats by birds, fish, and mammals; and recreational use. Monitoring
began two years prior to project construction and continues. The first
5 years of the monitoring program resulted in the following:
- Hydrodynamics. Post-project monitoring indicated that secondary
channel discharges to Weaver Bottoms were reduced 80 percent, and
hydraulic residence time was increased to between 3 and 7.6 days.
Current velocities within Weaver Bottoms have been reduced 60 to 90
percent. The two islands have altered flow patterns. However,
hydrodynamic impacts of the islands on Weaver Bottoms were small
compared to the reduction in inflow due to closure of secondary
channels. Wave action continues to be a major factor influencing bottom
velocities and sediment resuspension.
Since project construction, the need for dredging has decreased
dramatically (by 60 percent) in the Weaver Bottom area. This reduction
was probably due to greater channel scouring caused by the increased
river flows.
- Sedimentation. Bathymetry data from 1986 (pre-project) and 1991
(post-project) were compared with 1935 data. Construction of the
project resulted in notable changes in erosion/deposition patterns in
Weaver Bottoms. Although the net change in bathymetry from 1986 to 1991
was small, high rates of both deposition and erosion occurred. This
fluctuation indicated that internal factors, such as wind generated wave
action, have increased their influence on the sedimentation patterns in
Weaver Bottoms.
General patterns showed deposition in deep areas and erosion in
shallow areas. Three areas in particular showed bathymetry changes
since project construction: (1) One area with historically substantial
erosion showed significant reduction of erosion since inundation; (2)
the delta areas at side-channel openings along the main channel side of
Weaver Bottoms showed both deposition and erosion; and (3) an area near
the mouth of the Whitewater River showed increased rates of delta
expansion as a function of reduced flow velocities into Weaver Bottoms
following project construction.
- Water Quality. One project objective was to increase water clarity
and thus improve vegetation growth. Water quality in Weaver Bottoms did
not improve within the first 3 years following construction. Reduction
of inflow from the Mississippi River also reduced mixing and flushing
rates in Weaver Bottoms. Water quality in downstream portions of the
backwater area became more influenced by the Whitewater River, a turbid
river which empties directly into Weaver Bottoms. Variation in water
quality values increased among areas within Weaver Bottoms after project
construction as a result of differences in residence time.
- Vegetation. Between 1985 and 1990, a general decline in emergent
and submergent aquatic vegetation was recorded in the Weaver Bottoms
Rehabilitation Project area as well as in other areas of the Upper
Mississippi River. The cause of the vegetation loss is unclear but is
apparently related to the 1987 to 1989 drought and not due to project
construction.
- Birds and Mammals. Aerial waterfowl transect surveys were
conducted each fall from 1985 through 1990. Waterfowl use-days
increased substantially between 1986 and 1987, but sustained a steady
decline during the remaining post-construction period of 1988 to 1990.
Annual diving duck (mostly canvasback, Aythya valisineria) use-days were
more than double that of puddle ducks during the 1985 to 1987 period,
but were below or nearly equal to puddle duck use-days for 1988-90. This
post-construction decline in diving duck use probably reflected the
drastic losses of American wildcelery (Vallisneria americana), a
preferred canvasback food, in Weaver Bottoms during 1989 and 1990. Total
use-days of another common migratory waterfowl in the area, tundra swan
(Cygnus columbianus), varied but were lowest in 1989 and 1990 when
substantial declines in arrowhead (Sagittaria spp.) biomass were
detected.
Losses of vegetation and waterfowl use on the Weaver Bottoms
project area were not attributable to the rehabilitation project, as
evidenced by similar losses in nearby Upper Mississippi River pools.
Changes in continental populations, habitat conditions, and weather also
influenced migratory bird use of the river. The occurrence of muskrat
(Ondatra zibethica), shorebirds, gulls, and terns at Weaver Bottoms was
monitored, but no population trends were detected.
- Fish. Fish populations were monitored within and outside the
Weaver Bottoms project area. Trap nets, experimental gill nets and
electroshocking collection methodswere used. Pre- construction sampling
yielded 9,323 fish, epresenting 69 species with an average weight of 264
grams per fish. Post-construction sampling yielded 16,992 fish,
representing 57 species with a higher average weight of 271 grams per
fish. All sample methods showed an increase in catch per unit effort
during the post-construction years. The proportion of sport fish, rough
fish, and forage fish captured showed little change between pre- and
post-construction periods.
Four key species were identified at Weaver Bottoms: northern pike
(Esox lucius), carp (Cyprinus carpio), bluegill (Lepomis macrochirus),
and black crappie (Pomoxis nigromaculatus). Gill netting data shows a
biomass increase for all four species in the post-construction period;
carp increased the most. Similar increases in the four species at
stations within and outside Weaver Bottoms indicates that population
increases may be partially due to factors other than the rehabilitation
project.
Short-term monitoring results.
Phase I of the Weaver
Bottoms Rehabilitation Project had been constructed to improve habitat
quality within Weaver Bottoms and to reduce maintenance requirements of
the adjacent navigation channel. Results of the monitoring effort
indicate that there has been little immediate influence of the project
on habitat quality for vegetation or wildlife in Weaver Bottoms or in
adjacent areas of those studied. However, results indicate at least a
short term reduction in channel maintenance requirements during the
first 4-year period following Phase I construction.
More information about the project is available from Mary Davis at
(601)634-2853, e-mail:
mdavis@elmsg.wes.army.mil.
Back to Contents